Frequently Asked Questions
We’re carrying out this work on behalf of the Plasdŵr housing development, which will help manage the increased sewerage flow that we are expecting as the development progresses. We’re working closely with the local authority and the developer to ensure the Cardiff sewerage network has the capacity to be able to deal with these increased flows, and thus reduce the risk of network failure for the wider community.
Our work involves connecting the sewer pipe that runs from Danescourt to a connection point located the other side of the River Taff.
Working closely with our designers and the local authority, it has been agreed that the best solution to manage the additional flows would be to build a pumping station within Hailey Park which the sewer pipe will connect to. Planning for this pumping station was submitted in October 2021 and was granted in September 2022.
As part of our work, we’ve been working closely with the local authority and the developer to ensure the Cardiff sewerage network has the capacity to be able to deal with these increased flows that we are expecting as the development progresses, and thus reduce the risk of network failure for the wider community. We have identified that the sewerage network in Llandaff North has sufficient capacity for us to transfer some of the flows into this network which will then be taken to Cardiff Wastewater Treatment Works to be treated.
As part of this process we have been working hard to ensure we identify the best solution to accommodate the site, without causing any detriment to the local environment or the service we provide to customers in the area.
All other flows will be fed into the network and carried to Cog Moors Wastewater Treatment Works in Dinas Powys.
We were planning to start our work in Hailey Park and Danescourt this month (February 2023). However, due to a number of outstanding issues and the close proximity of the bird-nesting season, we are now planning to begin work on site in September. We will continue with our preparations and keep the construction timetable under review. As soon as a new start date is confirmed we will let local residents and stakeholders know.
The work is being funded by the Plasdŵr housing developers.
For the Plasdŵr development, the surface water removal will need to be undertaken in advance of the discharge of any foul flows from the development site over and above what has previously been agreed to discharge into the immediate public sewer in the vicinity of the site. The housing developer is funding these works which typically involve the redirection of surface water or highway drainage flows which currently enter the public combined sewerage system, into alternative outlets such as dedicated surface water systems, watercourses and culverts.
We have been developing a range of potential surface water removal schemes within the catchment to offset the new foul flows being generated from the development site. A number of those schemes are currently being assessed to prove their viability and selection and we’ll share more information at the appropriate time when we have more certainty about which schemes we will progress. These schemes will improve environmental outcomes and will not give rise to any environmental effects.
We are aware of the Judicial Review with Cardiff Council which challenges their decision. However, our planning permission still stands and subject to Welsh Water completing conditions of the planning consent, work can begin.
De Braose Close, Danescourt
We have looked at various solutions to be able to manage the additional sewerage flows from the Plasdŵr development. We have looked at various solutions to be able to manage the additional sewerage flows from the Plasdŵr development. Where possible, some of the new properties will be connecting into our nearby existing sewers where there is sufficient capacity. Where this is not feasible, the only viable option is to pass flows into one of our existing trunk sewers which carries flows to Cardiff Wastewater Treatment Works. To achieve this, we need to be able to cross the Cardiff to Radyr railway line and the River Taff, and we are working closely with both Transport for Wales and Natural Resources Wales in respect of this. The only workable location to do this with the Civil Engineering techniques that are going to be required has been identified within the area behind De Braose Close.
The content of a Local Development Plan (LDP) is a matter for the local planning authority. From a water and sewerage company perspective, how a development site is serviced is something that happens after the publication of the LDP when the developer shows an interest in the land and applies for Outline Planning Permission.
Following our work, we will need a permanent access to our assets in case of an operational incident. To do this, we are proposing to reduce the size of the existing track from five metres wide to three metres wide, as well as enhancing the area with additional trees and wildflower. Our proposal for this is outlined on the plan below and will go through the necessary permission process before being approved.
We are currently discussing our security options with our operations team, but some sort of restriction will be place at the top of the access track to stop motorised vehicles coming into the area.
No, there will be no overflow into the River Taff as a result of this work.
Hailey Park
Where possible, some of the new properties will be connecting into our nearby existing sewers where there is sufficient capacity. Where this is not feasible, the only viable option is to pass flows into one of our existing trunk sewers which carries flows to Cardiff Wastewater Treatment Works.
Normally, our network relies on gravity for waste to flow from your homes and businesses to our sewers. However, in low-lying areas – like Hailey Park – we need to pump the wastewater up into the network. To do this, we need to build a new pumping station which will pump the sewerage up to the existing sewerage network which will then travel to Cardiff Wastewater Treatment Works.
The location of the pumping station has been made based on the location of our sewer pipes and the availability of suitable land.
We are expecting increased sewerage flows in the Cardiff wastewater network as the development progresses. Some of these sewerage flows will travel to Cardiff Wastewater Treatment Works on Rover Way. Therefore, we need to ensure that the sections of the network which have sufficient capacity – such as Llandaff North – are able to carry these flows and thus reduce the risk of network failure for the wider community. This solution also causes least disruption to not only the local area, but the wider Cardiff community.
The pumping station site will be 24 metres by 21 metres. The pumps themselves will be 20 metres below ground, with a concrete cover at ground level.
There will be a kiosk which will be 3 metres high, and the fencing around the site will be 2.4 metres high. The fencing is green and has been designed to try and blend in with the landscaping around the site. It has also been chosen with security of our assets in mind. However, we are open to looking at alternative solutions to doing all we can to ensure the site blends in with its surroundings.
In line with legislation, we were not required to submit planning application for the assets below ground.
As part of our planning application, we have undertaken an Ecological Impact Assessment. This assessment includes multiple mitigation proposals and concludes that it is unlikely the proposed development will have negative impacts to the ecological receptors on site and in the local area.
It is considered that the biodiversity of the site will be maintained at a level that will retain the ecosystem’s function. There is no net loss to the vegetation within the site due to the replanting of native shrub species. The diversity and condition of the retained and created vegetation and grassland habitats within the site will be slightly increased through native species-rich planting and secured through long-term habitat management and monitoring.
As part of our landscape design, we are planning to reinstate the area using the following:
- Existing grass with ecologically enhanced meadow
- Native shrub mixes
- Wildflower meadow
- Trees
For full details please click here.
Access to the pumping station location will be via the existing access track (to the changing rooms) off Ty Mawr Road. All construction traffic will be coming through Whitchurch, via Velindre Road and Ty Mawr Road.
We will be constructing the access within the pumping station site using a grid structure that allows drainage and grass to grow through cells – this will help minimise the amount of concrete needed.
Yes, throughout the planning and design stages we have been working closely with Arup and their ecology resources.
As part of our work, we will need to remove some vegetation and trees to create a safe working environment. We are currently planning to do this in February 2023 and we are working with an ecologist and Cardiff Council to do this.
We have developed a comprehensive replanting programme which has an opportunity to boost the value of the local environment. This will be carried out once the work has been completed. For full details please click here.
Flooding impacts have been considered and have been factored into our choice of materials to reduce the risk of any flooding within the park as a result of our work. You can read more in section “5.6 Flooding Impacts “ in the planning application letter that is available on the planning portal
Where possible, all retained and created habitats on site will be enhanced for local biodiversity. This will include the installation of five bird boxes and five bat boxes to the north of the site, and the installation of an insect house and hedgehog house with the site adjacent to the scrub areas.
We have three kiosks proposed for the site; one to control the pumps, the second containing a potable water supply and a third which will contain an emergency generator which will keep the pumping station in operation should we experience a power outage.
The plastic material chosen for the kiosks is needed to meet design, construction and security requirements set out by legislation.
We will do all we can to ensure that public access routes remain open while we carry out our work – this includes access to facilities such as the changing rooms off Ty Mawr Road. However, for the safety of the general public there may be some diversions in place while we work. What this will look like will be communicated closer to the time when we are ready to start building the pumping station.
The pumping station has been designed to national standards which aim to eliminate noise and odours. Our pumps will be located 20 metres below ground with a closed, concrete shaft. The only above ground asset that could generate some noise is the emergency power generator, which would only be used during a local power outage.
The work is being funded by the Plasdŵr housing developers.
During the design and planning stages, we considered different options which were ultimately disregarded due to their feasibility and significant disruption that it would cause across the whole of Cardiff.
As part of this process we have been working hard to ensure we identify the best solution to accommodate the site, without causing any detriment to the local environment or the service we provide to customers in the area.
The area of land in Hailey Park where we are proposing to do our work is owned by Cardiff Council.
To say thank you to the community, we will be launching a £10,000 community fund in January 2023. The grant will be available to local community groups or organisations as a way of thanking them for bearing with us while we carry out our work. More information can be found here on the main page.
The pumping station has been designed as small as possible whilst allowing our operational team to access the assets for maintenance purposes, creating a safe environment for park users.
Access to the pumping station will be via the existing access track to the changing rooms off Ty Mawr Road. During construction, there will be more traffic than usual travelling in the area. However, this will be mostly at the start and the end of the project when we are setting up and demobilising our compound. When construction work is underway, vehicles will be less frequent. There will not be hundreds of deliveries made each day.
Once completed, we do not envisage the current access track security arrangements needing to be changed. Welsh Water maintenance vehicles will occasionally visit the site, but this will not be on a regular basis.
We have been working closely with all the necessary stakeholders to ensure the park remains a safe place for people to enjoy while we carry out our work. Once built, the new pumping station will not result in any reduction to existing rugby pitch provision. During construction work however, one pitch will be impacted. All relevant parties are aware of this and alternative arrangements have been agreed.